Lane closures continue in Koloa

KOLOA — Multiple sections of Koloa Road and Maluhia Road are scheduled for lane closures from Monday to Wednesday, May 3 to 5.

Multiple sections of Koloa Road will be under a single-lane closure for shoulder construction, pavement work and striping operations from 7 a.m. to 6 p.m. Portions of Maluhia Road will also be under short lane closures for inspection and punch-list completion work from 7 a.m. to 6 p.m.

Construction of the Koloa Road roundabout is currently projected to be complete by May 25.

The current projected project final completion date is July 13.

1 Comments
  1. marl May 2, 2021 8:59 pm Reply

    Please explain- round about to be completed by 5/25/21- but next sentence says final completion by 7/31/21–


Your email address will not be published. Required fields are marked *

*

By participating in online discussions you acknowledge that you have agreed to the TERMS OF SERVICE. An insightful discussion of ideas and viewpoints is encouraged, but comments must be civil and in good taste, with no personal attacks. If your comments are inappropriate, you may be banned from posting. To report comments that you believe do not follow our guidelines, send us an email.